Set 10 of the Advanced Training for Liquefied Gas Tanker Cargo Operations (GASCO) exit exam bank — 30 of 351 questions, with the correct option marked and a one-line explanation for every one. Read it end to end, jump to a single set, or search it — then sit the same bank as a timed paper. The real DG Shipping exit exam is 30 marks with 15 to pass.
These are the bank's original groupings. Practising deals the whole bank out again every time you reshuffle, so a practice “Set 3” is a different 30 questions each time — the set numbers below are the source file's, and are only used here so the key stays navigable. Options are listed in their original order with fixed letters; when you practise, those move too.
Bank last rebuilt .
30 of 30 shown · Set 10
Nothing in this set matches that. Try a shorter word, or search the whole key.
Set 10 — 30 GASCO exit exam questions with answers
1. What is the agreement between the buyer and the end-users called as?
- A. Sale and Purchase Agreement(SPA)
- B. Delivery Ex-Ship (DES)
- C. Gas sale agreement(GSA)
- D. Free On Board(FOB)
2. Identify the odd one out. Which of these factors will not increase the boil-off onboard an lng carrier?
- A. Detoriation of insulation barriers
- B. sloshing in the cargo tanks
- C. Rasing of insulation space pressure
- D. Long loaded passage
3. the methods used for producing inert gas onboard LNG carriers are many, which one method may no longer be used?
- A. By stoichiometric combustion in an inert gas combustion
- B. flue gas from main boilers
- C. Nitrogen by fractional distillation or by pressuree swing absorbtion(PSA)
- D. Nitrogen by turning liquid nitrogen from shore to nitrogen gas
4. Which law states that the sum of the partial pressures of the constituent gases of a mixture of gases is equal to the total pressure of the gas mixture?
- A. Boyle's law
- B. Gay Lussac's law
- C. Charles's law
- D. Dalton's law of partial pressure
5. What is the quantity of heat absorbed on vaporization at normal boiling point?
- A. Vaporization heat
- B. Latent heat
- C. Condensation heat
- D. lost heat
6. During normal loading/ discharging cycle, how does keeping the tanks cool and ready for loading help?
- A. It reduces the thermal stresses on the membrane
- B. It increases the ship operation costs
- C. It increases thermal stresses on the membrane
- D. It reduces boil-off in the ballast passage
7. Find the correct answer. A vessel certified to carry an NLS(Noxious liquid substances) must comply with
- A. OSHA regulations
- B. International Pollution Prevention Certificate for the carriage of Noxious liquid substances
- C. STCW regulations
- D. ILO regulations
8. Based on the principles of segregation, what would you classify the cargo compressor room?
- A. Gas safe spac
- B. Gas safe zon
- C. Gas dangerous zon
- D. Gas dangerous spac
9. Which of the following are not the early signs of structural failure of the inner hull?
- A. Increasing of Lng level in cargo tanks, by incoming seawater
- B. Water detected in secondary insulation spac
- C. Further lowering of insulation space temperature sensed by the thermocoupl
- D. Maximum methane reading detected by the explosive meter inside insulation spaces
10. Insulation materials for use on liquefied gas carriers shall possess the following, except:
- A. ability to bear physical loads
- B. Ingress of moisture is not possible thereb, loss of insulation performanc
- C. ability to withstands mechanical damage
- D. reasonably lightweight
11. How is the formation of cold spots on the inner hull surfaces which is not fitted with thermocouples detected?
- A. By using remote ice detection device at any tim
- B. frequent inspections of inner hull on ballast passage
- C. By using remote lng leak detector any tim
- D. frequent inspections of inner hull on loaded passage
12. What will happen if the primary space is at least partially flooded with LNG?
- A. No reduction in exhaust flow to atmosphere or increase in the temperature of the secondary spaces
- B. Changes in exhaust flow to atmosphere and increase in the temperature of secondary spaces
- C. Reduction in exhaust to atmosphere or decrease in the temperature of secondary spaces
- D. Pressure insulation will increase and temperature for primary spaces will reduces
13. Onboard an LNG tanker with NO 96 containment system, with minor membrane leakage, which of the following it not a recommended remedial action?
- A. Check and log gas concentration and temperature on the damageed insulation spaces frequently
- B. Ensure at all times secondary space pressuree>damageed primary pressuree +0.5 to 10 bar
- C. Alter ship's course and speed to increase pressuree within damageed insulation spaces
- D. Check location of crack by using vent cock located on nitrogen supply and exhaust
14. What remedial action should be taken as soon as possible prior discharging cargo from a damaged cargo tank?
- A. Fix the equalizer between gas dome and secondary insulation spac
- B. Fix the equalizer between gas dome and primary insulation spac
- C. Fix the equalizer between primary and secondary spaces
- D. Fix the equalizer between gas dome and vacuum lin
15. Each equipment on LNG ship will be stamped with Information giving the type of protection. That will not include,
- A. Ex d IIb T6 means that the equipment is certified Ex d protected by explosion proof enclosur
- B. Ex d protected by explosion proof enclosur
- C. IIb gas group
- D. 17 temperature class -100°C
16. Onboard a membrane type LNG carrier, why does the primary membrane have a tendency to collapse during discharge of cargo from damaged cargo tank?
- A. Due to different material use for cargo tank and primary membrane
- B. Due to temperature variations
- C. Due to large different liquid level
- D. Due to small different liquid level
17. Which of the following machinery is used for power generation onboard an LNG Carrier with a steam turbine plant?
- A. A forcing vaporizer
- B. A diesel generator
- C. A degasification unit
- D. A reliquefaction plant
18. Onboard an LNG carrier, with NO 96 membrane containment system, what is the indication of failure of the primary membrane and primary insulation space?
- A. Temperature drop in secondary space temperature probes
- B. Temperature drop in cofferdam space temperature probles
- C. Temperature drop in wing ballast tank space temperature probles
- D. Temperature drop on main deck temperature probles
19. How does the gas detection system react to a minor leak of primary barrier spaces?
- A. Gas percentage methane content will increase depending on the location and size of the crack
- B. Gas percentage oygen content will reduce depending on the location and size of the crack
- C. Gas percentage nitrogen content will increase depending on the location and size of the crack
- D. Gas percentage methane content will decrease depending on the location and size of the crack
20. Which of the following is not a typical counter measure carried out after a major membrane leak or failure?
- A. Isolate primary spaces of affected cargo tanks
- B. Stop gas burning in boilers
- C. Open primary spare exhaust of affected cargo tanks to vent excess pressure
- D. Closely monitor all temperature sensors and gas detection system of the affected cargo tank
21. Onboard an LNG tanker with NO 96 containment system what will typically happen if a minor membrane leak(crack) occurs below the cargo level?
- A. Big flow of liquid into the crack will rapidly vaporize and cargo will be severely damageed
- B. Small flow of liquid into the crack will vaporize cargo tank pressuree will increase tremendously increase tremendously
- C. Big flow of liquid into the crack will vaporize and colaps the primary membranee inwards
- D. Small flow of liquid into the crack will vaporize, cargo tank will remain the sam
22. The grade of steel used for inner hull construction is designed so to withstand
- A. The main pressuree can be created by UNG voor in an enclosed spac
- B. The minimum temperature due to LMG contact
- C. The minimun corrosion effect due to steel-air and seawater contact
- D. The maximum explosion force that can be created by LNG vapor in an enclosed spac
23. Identify the odd one. Each main cargo pump electric motor is protected from certain faults. Which of the following is an exception?
- A. Delayed start
- B. Thermal overload (over current)
- C. Undercurrent (no load operation)
- D. Imbalance between phases (single-phasing)
24. Why does the cofferdam heating system have two sets of heating coils?
- A. One for starboard and one for port
- B. One for upper and one for lower
- C. One in service and one on standby
- D. One for forward part and one for aft part
25. In an LNG carrier two types of cargo pumps are fitted in each cargo tank. Identify them by name.
- A. Big cargo and small cargo pumps
- B. Emergency and small cargo pumps
- C. Main cargo and stripping/spray pumps
- D. Emergency and big cargo pumps
26. What are the two types ur heating medium which may be used for the typical cofferdam heating system onboard LNG carers?
- A. Seawater or R 404a
- B. Steam or glycol water
- C. Warm air or brin
- D. Alcohol solution or seawater
27. Capacitance type gauges are reliable as they have no moving parts. Identify the condition under which they may fall?
- A. Presence of nitrogen and methan
- B. Presence of water, dirt or rust
- C. When the tank is empty
- D. When the tank is not full
28. IGC Requirements on LNG vessels are stated below that will not include
- A. The Gas Codes and classification society rules require every cargo tank to be fitted with at least one squid level gaug
- B. The Gas Codes require every cargo tank to be fitted with at least two liquid level gauges
- C. Chapter 19 of the 1GC code provides the requirements for gauging systems usiing onboard gas carriers.
- D. This information is summarized in Appendix 2 of the same code.
29. In ESDS pneumatic link system which equipment is used to sense and monitor the air pressure in the system so that the ESDS will activate if the air pressure in system Fall below set point
- A. Pressure regulator
- B. Pressure switch
- C. Pressure control valv
- D. Pressure dumping valv
30. Why should the temperature of cofferdam and liquid domes be maintained above +5°C
- A. To ensure no heat transfers from seawater through outer hull
- B. To equal The Teperatures of the containment system and insulation spaces
- C. to ensure space is warm for inner hull inspection
- D. If inner full temperature drops to sub-zero temperatures, it can suffer structural damage