Set 6 of the Oil and Chemical Tanker Cargo Operations (OCTCO/OCTF) exit exam bank — 30 of 252 questions, with the correct option marked and a one-line explanation for every one. Read it end to end, jump to a single set, or search it — then sit the same bank as a timed paper. The real DG Shipping exit exam is 30 marks with 15 to pass.
These are the bank's original groupings. Practising deals the whole bank out again every time you reshuffle, so a practice “Set 3” is a different 30 questions each time — the set numbers below are the source file's, and are only used here so the key stays navigable. Options are listed in their original order with fixed letters; when you practise, those move too.
Bank last rebuilt .
30 of 30 shown · Set 6
Nothing in this set matches that. Try a shorter word, or search the whole key.
Set 6 — 30 OCTCO/OCTF exit exam questions with answers
1. The total capacity of all slop tanks on an oil tanker normally should be?
- A. 1% of the total oil carrying capacity of ship
- B. 2% of the total oil carrying capacity of ship
- C. 3% of the total oil carrying capacity of ship
- D. 4% of the total oil carrying capacity of ship
2. In chemical tankers the coding system used by the IBC Code for an independent tank is?
- A. 1
- B. 2
- C. G
- D. P
3. Which of the following is cofferdam?
- A. Chain locker
- B. Pump room on an oil tanker
- C. Deep tank
- D. Slop tank on an oil tanker
4. The purpose of a cofferdam between two compartments is to?
- A. Store tools and equipment that are necessary for the adjacent compartments
- B. Give access to the bulkhead for inspection and repairs when the tanks are full with liquid
- C. Keep a reserve space if the capacity of either compartment needs to be increased
- D. Prevent different liquids from the two tanks coming in contact in case of a leak
5. Which pump must always be primed?
- A. Centrifugal pump
- B. Reciprocating pump
- C. Rotary pump
- D. Gear pump
6. What does "VECS" stand for?
- A. Vector control system
- B. Vapor emission control system
- C. Very economical control system
- D. An arrangement for release of cargo vapor
7. The minimum safety during EGB soot blow must be carried out with?
- A. The OOW & Masters consent avoid soot blow during the purging time
- B. Any time excluding the dark night hours
- C. At 12 hours interval
- D. At 8 hrs. interval
8. Why is a warning sign displayed at the gangway or access point of a barge during cargo transfer?
- A. To indicate any health risk if applicable
- B. To keep visitors away from the barge-No smoking, no open lights, no visitors
- C. To designate smoking areas
- D. To indicate if the cargo is a marine pollutant
9. Oxygen deficiency will begin to cause problems to personnel, do you feel to measure the atmosphere before entering clean Tanker?
- A. Not necessary for ballast tanks
- B. Always necessary for ballast tanks
- C. Not necessary if the tank is filled up twice and discharged at sea
- D. Not necessary if the tank is ventilated by external fans
10. Which party is responsible for arranging the reducers or enlarger short pieces to the manifold?
- A. The Cargo supplier
- B. The Cargo Surveyors
- C. The Ships Mooring crew
- D. The tankers staff for the operation
11. Very light gaseous molecules such as ______ are extracted at the well head?
- A. Methane
- B. Butane
- C. Propane
- D. None of these
12. In the event of a pneumatic remote-control failure in the inert gas plant I/P and E/P controllers, during discharge _____?
- A. The inert gas plant must be operational within one hour of failure and the discharging may continue for this time
- B. The discharge must be immediately halted
- C. The discharge rate must be reduced until the plant is repaired
- D. The venting of IG is set to maintain a predetermined pressure and the discharge can continue manually
13. When the IG plant is shutdown, the IBC cooling water should be let on the scrubber for at least ____hour(s)?
- A. 1
- B. 2
- C. 3
- D. 4
14. What are consequences of a high oxygen content alarm sound during normal operation?
- A. The plant is shut down
- B. The pressure control valve and the flue gas isolating valve will automatically close
- C. The alarm in Ccr will sound loud and the plant will auto stop
- D. The deck demand valve will automatically close. The atmosphere purge valve will open and the furnace presser control valve will regulate.
15. What are these types of tanker: -LR1 (large range 1)?
- A. 25,000-49,999DWT
- B. 50,000-79,999 DWT
- C. 80,000-159,999 DWT
- D. None Of the Above
16. The petroleum remaining after the removal of products such as methane is termed_______?
- A. Crude oil
- B. Diesel oil
- C. HFO
- D. None Of These
17. PROTECTION for acetylene & oxygen line flame arresters & N/R flow back valves are for?
- A. Carrying out gas welding & acetylene gas cutting work
- B. Protection of personnel from high temp.
- C. Preventing sparks from entering a tank or vent opening
- D. Fire fighting
18. In case of P/V valve for one tank is not working and the tank pressure is rising, what immediate actions are necessary usually set to follow?
- A. Abort filling that individual tank
- B. Try to open the valve manually
- C. Isolate the line and change the valve from vessels tested spare
- D. Follow all the procedures (A) + (B) &(C)
19. Which topic is not required to be discussed at the pre- transfer conference?
- A. Estimated time of finishing cargo
- B. Details of transfer and receiving system
- C. Emergency shutdown procedures
- D. Identity of the product to be transferred
20. Examples of inorganic chemicals such as:
- A. Sulphuric acid
- B. Phosphoric acid
- C. Nitric acid
- D. All of the above
21. Clean ballast is normally______?
- A. Ballast water loaded directly into a cargo tank after discharge
- B. Ballast water into cargo tanks which have been washed crude oil
- C. Ballast water loaded into cargo tanks which have been crude oil and water washed
- D. Ballast water loaded in designated tanks used only for that purpose
22. During loading operation ullage and temp measuring equipment is showing low battery which place can we replace battery?
- A. Can be replaced on tank area
- B. Can be replaced near manifold area
- C. Can be replaced at pump room entrance
- D. Can be replaced only with indoor accommodation
23. Vessels in clean service normally do not have or need heater coils as the viscosity of the clean product is low enough to permit easy pumping at atmospheric temps.
- A. Applies to all clean petroleum products (CPP)
- B. With the exception of some lube oils & special vegetable oils
- C. Applies to all chemicals
- D. Applies to all condensates
24. The foam system is operated from the _____room?
- A. CCR
- B. ECR
- C. FGFC
- D. All the above
25. MARPOL Annex VI applies:
- A. Only the ships that fly the flag of a state that is party to MARPOL annex VI
- B. Only to ships that visit ports of a state that is party to MARPOL annex VI
- C. To ship with both of the above
- D. All ships irrespective of flag or port state control requirements
26. Inert gas after leaving the demister will consist of the following?
- A. Oxygen less than 5%
- B. SO2 less than 2.0%
- C. Water vapor 1%
- D. Both A & B
27. How much volume of air needs to be changed in pump room?
- A. 10 vol/hr.
- B. 25 vol/hr.
- C. 20 vol/hr.
- D. 15 vol/hr.
28. Fixed foam monitors having a operating capacity_____L/min?
- A. 1250
- B. 1450
- C. 1150
- D. 1650
29. In tankers, the central equipment is available either for installation in _____locations.
- A. Hazardous
- B. Non-hazardous
- C. Under – pressurized
- D. All of the above
30. The physical data of a liquid chemical can be found on_____?
- A. MSDS (material safety data sheets)
- B. The Information supplied by the manufacturer
- C. ICS cargo data sheet
- D. All of these a), b) & c)