GASCO exit exam questions and answers — Set 24 — Advanced Training for Liquefied Gas Tanker Cargo Operations
Set 24 of the Advanced Training for Liquefied Gas Tanker Cargo Operations (GASCO) exit exam bank — 20 of 710 questions, with the correct option marked and a one-line explanation for every one. Read it end to end, jump to a single set, or search it — then sit the same bank as a timed paper. The real DG Shipping exit exam is 30 marks with 15 to pass.
These are the bank's original groupings. Practising deals the whole bank out again every time you reshuffle, so a practice “Set 3” is a different 30 questions each time — the set numbers below are the source file's, and are only used here so the key stays navigable. Options are listed in their original order with fixed letters; when you practise, those move too.
Bank last rebuilt .
20 of 20 shown · Set 24
Nothing in this set matches that. Try a shorter word, or search the whole key.
Set 24 — 20 GASCO exit exam questions with answers
1. Cargo tank pressure relief valves on gas carriers are sized primarily for which design case?
- A. Fire exposure of the tank, plus vapour from purging or other sources
- B. Normal boil-off at sea
- C. Maximum loading rate only
- D. Thermal expansion of liquid in the lines
2. Apart from relief valves, what does the IGC Code require for a cargo tank not designed to withstand the maximum external pressure difference?
- A. Two independent pressure switches to alarm and then stop suction of liquid or vapour from the tank, or vacuum relief valves
- B. A gas-freeing fan permanently connected
- C. A second spool piece at the manifold
- D. A water spray nozzle inside the tank
3. What is the main advantage of a pilot-operated relief valve over a simple spring-loaded valve on a low-pressure cargo tank?
- A. It stays tight close to its set pressure and opens fully with little overpressure, giving accurate settings at low pressures
- B. It does not need to be tested or maintained
- C. It can only lift when the vent mast is on fire
- D. It can be set above MARVS
4. What is the purpose of the nitrogen purging/snuffing connection at the top of an LNG carrier's vent mast?
- A. To extinguish a fire at the vent outlet caused by ignited vented vapour
- B. To raise tank pressure during discharge
- C. To dry the cargo tanks before loading
- D. To supply nitrogen to the insulation spaces
5. Under IGC Code chapter 18, the closing time of ESD valves at the manifold, measured from activation to final closure, must normally not exceed:
- A. 30 seconds
- B. 5 seconds
- C. 2 minutes
- D. 5 minutes
6. To avoid surge pressure, how does the IGC Code relate the maximum loading rate to the ESD valve closing time?
- A. Loading rate in m³/h should not exceed 3600 U/t, where U is the ullage volume at the operating signal level and t the time to stop flow
- B. Loading rate should equal the shore pump capacity
- C. Loading rate should be reduced only when topping off the last tank
- D. There is no relationship; closing time is fixed
7. In SIGTTO terminology, what distinguishes ESD-2 from ESD-1 on a loading arm system?
- A. ESD-2 activates the powered emergency release coupling to separate the arms, after ESD-1 has stopped the transfer
- B. ESD-2 only sounds an alarm
- C. ESD-2 restarts the cargo pumps
- D. ESD-2 opens the manifold valves
8. What is the key safety feature of an emergency release coupling (ERC) on a liquefied gas loading arm?
- A. Two valves close either side of the coupling before it separates, so only a small amount of liquid is released
- B. It cuts the arm with a hydraulic blade
- C. It allows the arm to stretch to follow the ship
- D. It vents the arm contents to atmosphere before release
9. When should the ship-shore ESD link be tested during a cargo port call?
- A. After connection and before cargo transfer starts, as agreed at the pre-transfer meeting
- B. Only during dry-dock
- C. Only after discharge is complete
- D. Only if a leak has occurred
10. Why is a fibre-optic ship-shore link often preferred to an electrical link at LNG terminals?
- A. It can also carry telephone and data signals, is immune to electrical interference and carries no spark hazard
- B. It does not need a connector at the manifold
- C. It works without any shore equipment
- D. It replaces the need for ESD valves
11. What happens to the ship's ESD system if electrical or control-air power to it is lost?
- A. It is designed to fail safe, closing the ESD valves and stopping cargo transfer
- B. The valves stay in their last position until power returns
- C. Only an alarm is given and transfer continues
- D. The cargo pumps speed up to finish quickly
12. During a planned stop, why should cargo flow be reduced and shore pumps stopped before ESD valves are closed?
- A. To prevent surge pressure from rapid valve closure against a full-rate flow
- B. To allow the ESD link to be disconnected faster
- C. To increase the boil-off rate
- D. To warm up the manifold
13. When gassing-up a cargo tank with methane vapour after inerting, how is the vapour introduced and the inert gas removed?
- A. Warm methane vapour is introduced at the tank top and the heavier inert gas is pushed out through the bottom filling line
- B. Methane is introduced at the bottom and inert gas vented from the top
- C. Liquid LNG is sprayed in at full rate with all vents closed
- D. Inert gas and methane are mixed by the tank fans
14. Why must inert gas from a combustion-type generator be replaced by cargo vapour before LNG cool-down?
- A. Its carbon dioxide would freeze at LNG temperatures, forming solids that can damage pumps and block valves and spray nozzles
- B. Inert gas reacts violently with LNG
- C. Inert gas makes the cargo off-spec only for odour
- D. Inert gas raises the boiling point of LNG
15. To what dew point should cargo tanks be dried before loading a refrigerated cargo?
- A. Below the lowest temperature the tank and cargo system will reach in service
- B. Equal to ambient seawater temperature
- C. 0°C in all cases
- D. Above the cargo boiling point
16. During the warming-up of LNG cargo tanks before gas freeing, how is the heat normally supplied?
- A. Cargo vapour is heated in the cargo heater and circulated to the tanks by the compressor
- B. Steam is injected directly into the tanks
- C. Seawater is pumped into the hold spaces
- D. The tanks are left open to atmosphere
17. Why are cargo tanks inerted after warming up and before aeration with dry air?
- A. To lower the hydrocarbon content so that the tank atmosphere does not pass through the flammable range when air is introduced
- B. To cool the tanks again
- C. To increase the oxygen content
- D. To prevent the cargo heater from overheating
18. Why is the loading rate reduced during topping-off of cargo tanks?
- A. To control the final level accurately and avoid exceeding the permitted filling limit or triggering high-level ESD
- B. To increase the boil-off rate
- C. To allow the tank to warm up
- D. To save shore pump power
19. On a laden LNG voyage, which parameters must be continuously monitored as part of care of cargo in transit?
- A. Tank pressures, cargo temperatures, levels and the operation of the BOG handling system
- B. Only the ballast tank soundings
- C. Only the manifold pressure
- D. Only the cargo pump motor insulation
20. During bulk loading of LNG at a terminal, how is cargo tank pressure normally controlled?
- A. Displaced vapour and flash gas are returned to shore through the vapour return line, using the high-duty compressor if needed
- B. Vapour is vented continuously through the vent mast
- C. The loading rate is kept at maximum and pressure ignored
- D. Tank pressure is controlled by opening the insulation space relief valves